Thresholds Tab of the Code File Properties Dialog Box

Use the Thresholds tab to define acceptable cost and schedule variances.

This tab controls which variances Cobra tracks for the selected code file. If you change the threshold settings on this tab, the threshold settings that you specified in the New Code File wizard when you were creating the code file will also change. When a cost variance or schedule variance exceeds the predefined threshold, they are highlighted in either red for unfavorable (negative) or green for favorable (positive). These thresholds, or tolerances, define how large cost variances (Earned Value - Actual Cost) and/or schedule variances (Earned Value - Budget) must be before Cobra triggers exception reporting mechanisms.

Note: Using thresholds is known as management by exception and is an efficient way to manage a project. Instead of micro-managing the entire project, you only focus on areas that exceed the predefined threshold.

Contents

Schedule Variance

A schedule variance is a metric for the schedule performance of a project. It is the algebraic difference between earned value and the budget (Schedule Variance = Earned Value - Budget). A positive value is a favorable condition while a negative value is unfavorable.

Field Description
Current period

This field refers to the schedule variance for the current period. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below.

Cumulative

This field refers to the cumulative schedule variance. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below.

Cost Variance

A cost variance is a metric for the cost performance of a project. It is the algebraic difference between earned value and actual cost (Cost Variance = Earned Value - Actual Cost). A positive value indicates a favorable position and a negative value indicates an unfavorable condition.

Field Description
Current period

This field refers to the cost variance for the current period. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below.

Cumulative

This field refers to the cumulative cost variance. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below.

At complete

This field refers to the cost variance at project completion. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below.

Threshold Options

Use the following options to define the threshold settings for the Schedule Variance and Cost Variance fields.
Value Description
None The code file will not use thresholds or tolerances.
Percent Cobra will define the schedule variance as a percentage amount.
Value Cobra will define the schedule variance as an absolute amount.
Both Cobra will define the schedule variance using both the percentage amount and the absolute value.